Getting AroundTop story
One lane of eastbound U.S. 54 at the Missouri River Bridge will close four nights
The U.S. 54 lane closure runs from 7 p.m. to 6 a.m.
Eastbound U.S. 54, Missouri River Bridge to north of Route W
- 7 p.m. to 6 a.m.Left eastbound lane closed
- Nights
- Wed., Thu., Fri. and Mon.
Sources: KOMU 8, Jefferson City News Tribune, KRCG
View as table
| When | What |
|---|---|
| 7 p.m. to 6 a.m. | Left eastbound lane closed |
| Nights | Wed., Thu., Fri. and Mon. |
If you cross the Missouri River Bridge into north Jefferson City at night, plan for one fewer lane. MoDOT will close the left eastbound lane of U.S. 54 from the bridge to north of Route W (Cedar City Road/Airport Road) while crews install a new overhead sign in the median.
Tonight is the second of four nights. The contractor is working around the clock on pavement at the Route W interchange, plus shoulders, guardrail and signs. The goal is to open the interchange, the ramp and a new dedicated lane for southbound U.S. 63 onto the bridge. The contractor's expedited schedule targets the end of 2026.
The U.S. 54 project is aiming to finish well ahead of its May 2027 deadline
- April 2026Missouri Highways and Transportation Commission awarded a nearly $4.2 million contract.
- June 2026Work began on expanding the westbound lanes of U.S. 54.
- End 2026The contractor's expedited schedule targets completion.
- May 2027The contract's deadline for completing the project.
Source: Jefferson City News Tribune
- Closed: left eastbound lane only
- Contractor: Don Schnieders Excavating Company Inc.
- Work is weather-permitting, and schedules are subject to change